Six-laning of Gurgaon-Kotputli stretch on NH-8 delayed

The Union Minister of State for Road Transport and Highways Sarvey Sathyanarayana has said that the six-laning work on Gurgaon-Kotputli stretch on National Highway No 8 has been delayed. The main reasons for delay are due to slow progress during construction by Concessionaire, delay in the land acquisition, delay in Forest Clearance, delay in removal of religious and other structures & additional works in the project scope owing to public representations etc.